Gulpur hydropower project: PPIB says decision to suspend work made in sheer haste
Private Power and Infrastructure Board (PPIB) said on Monday that Engineering, Procurement & Construction (EPC) contractor for 102MW Gulpur Hydropower Project made a decision in haste to suspend work and vacate the project site.
“With a security alert the requirement is to be vigilant and re-enforce security at the site. However, the contractor made a premature decision to stop work and vacate the site. PPIB is pursuing with concerned quarters for resolution of the matter at the earliest,” said, Sami Rafi Siddiqui, a spokesman for PPIB.
Published in Business Recorder, 8th August, 2017
http://epaper.brecorder.com/2017/08/08/1-page/896995-news.html
>